Highlights of Pecan Grove MUD Meeting – May 21, 2024

The regular monthly meeting of the Pecan Grove Municipal Utility District was held at the Pecan Grove Country Club at 3:30 p.m. on May 21, 2024. The next regular meeting is scheduled for Tuesday, June 25, 2024, in the PGMUD Community/Administration building at 12:00 p.m.

Fort Bend County Sheriff’s Office
Monthly Contract Report for May 2024

PGVFD Report – May 2024

Parks Report

The second water fountain at Pecan Grove Park is still waiting on delivery of parts to get it back in service.

The pavilion at Windmill Park was pressure washed in May.

The installation of the new workout equipment along the walking trail in Pecan Grove Park is scheduled to begin June 10, 2024, and should take about seven days to complete.

Operator’s Report – Si Environmental, LLC

April 2024 testing showed that the drinking water system met the state and federal compliance standard for disinfection and there were no permit excursions for the month.

At the SWTP the ClO2 batch tank B replacement has been completed. The replacement of the gate at the SWTP is in process and will be reimbursed by Fort Bend County. Replacement of the thickner torque monitor is complete as well as the shelter boxes. The repair of the flanged column piping on the High Service Pump is in process as well the replacement of the belt press poly feed system.

The replacement of the booster check valves #1 and #2 at Water Plant #1 is in process as is the replacement of the 4” incoming potable water RPZ backflow device at the WWTP.

The coffing hoist at the WWTP replacement is complete; the hand wheel operator at the North storm water pump station replacement is in process.

At the SWTP, the high service motor #3 will be replaced.

At Water Plant #1 8” Prop Meter and Totalizer will be replaced.

The inspection for district lines containing lead and or copper (pre-1989) mandated by the EPA has begun and must be completed by October 16, 2024. Of the 2,580 locations identified, the inspections have been completed on 545 or 21%.

The annual flushing of fire hydrants will begin the week of June 17th.

The program to replace high usage residence meters in the district has replaced 1,626 meters since January 2023 with 13 this month.

Please remember to call Si Enviro first, if you have an outside water leak.

Click here to view Projects Under Construction and Design.